The Ashrafiyeh – Jisr al-Touta road crosses the Ghab Plain in Hama countryside, linking Ashrafiyeh and Jisr al-Touta over about 10 kilometres and a width of 10 metres (SANA's Arabic reports write the second name as “Jisr al-Tout”). SANA reported that rehabilitation and paving works started on 7 April 2026 and that the road serves around 100,000 people.
The director of the Ghab region told SANA that the road is an extension of the road between the villages of Al-Huwayz and Al-Rasif. A Hama Governorate news item stated that the governorate is carrying out rehabilitation works on the road connecting the villages of Ashrafiyeh and Jisr al-Touta, in coordination with the Ghab Region Administration and the Directorate of Technical Services, as part of completing the Al-Huwayz – Al-Rasif road corridor.
The Ghab region director told SANA that the works include filling the potholes in the road surface, repaving the damaged sections and widening them as far as resources allow, and removing the rubble piled up on both sides. The governorate's news item, for its part, mentioned laying gravel and compacted base course layers along about 10 kilometres at a width of 10 metres, to address the deteriorated road infrastructure that affects residents' daily travel.
SANA notes that no rehabilitation works had been carried out on the road for several years.
The road connects Ashrafiyeh and Jisr al-Touta in the Ghab Plain of Hama countryside, and the director of the Ghab region described it to SANA as an extension of the road between the villages of Al-Huwayz and Al-Rasif.
According to SANA, the works cover approximately 10 kilometres in length at a width of 10 metres.
The Ghab region director told SANA that they include filling potholes, repaving damaged sections and widening them, and removing rubble from both sides of the road. Hama Governorate mentioned laying gravel and compacted base course layers.
SANA reported the start of rehabilitation and paving works on 7 April 2026.
SANA says the road serves about 100,000 people.
On 23 September 2026 SANA said that the Ashrafiyeh – Jisr al-Tout road was among the roads that saw rehabilitation and paving works in the recent period, without giving a completion percentage or finish date.
Decision to complete stalled projects. On 28 June 2026 the director of the Ghab region told SANA that the paving of the road between Al-Suqaylabiyah and Bridij follows a decision by the Ministry of Local Administration and Environment to complete projects stalled since 2011, and that legal procedures had been taken for a number of road projects in the Ghab region, among them the Ashrafiyeh – Jisr al-Touta road.
Al-Huwayz – Al-Rasif road. On 19 July 2026 SANA reported the start of rehabilitation works on the 4.5-kilometre Al-Huwayz – Al-Rasif road, supervised by the Technical Services Directorate in Hama and the Ghab Region Administration. In a second SANA report the same day, the head of the Technical Services Department in the Ghab said the works run in two stages: first dealing with potholes, cracks and sunken sections, then laying a second asphalt layer at least 6 centimetres thick and 5 metres wide. In April the region's director had described the Ashrafiyeh – Jisr al-Touta road as an extension of that road; SANA's two July reports do not mention the Ashrafiyeh road.
Current status. On 23 September 2026 SANA, in a report on residents' calls to repair the main roads of the Ghab, said that rehabilitation works had been carried out in the recent period on a number of roads in the area, including the rehabilitation and paving of the Ashrafiyeh – Jisr al-Tout road. The report gives no completion percentage, finish date, cost of the works or contractor name.